#WorksiteWednesday University of Idaho Administration Building
#WorksiteWednesday Even though temps have dropped over the last few weeks, the Campus Drive scope of work in front of the Administration Building at the University of Idaho is still underway! A&R Construction Inc. and their skilled team of sub-contractors are wrapping up the concrete pours and working hard to try and beat the snow. The poured-in-place concrete edges for the paver fields are in, drainage systems in place, and the paver installation will likely begin shortly. The custom cast bronze University of Idaho seal has been manufactured and is waiting to be placed in its final resting spot in the center of the circle. Coming up next will be the installation of the lighted brick pilasters flanking either side of the central sidewalk approach to the East, installation of the historic light poles, and landscaping to soften up the hardscape and set the stage for a show of color in the spring. The anticipated completion date of mid-December 2020.