Project Update from West of Jefferson Mixed-Use in Kendall Yards

Greenstone has completed the removal of a large amount of basalt rock and prepped the site for Baker Construction. Baker and their sub-contractor Everett Concrete are now hard at work installing both site and main level concrete necessary to complete the structural concrete podium. The completed work includes; retaining walls, footings, grade beams, portions of the elevator walls, and some of the columns for the concrete podium. Rebar and formwork are also being installed for the balance of the podium columns and one of the two stairwells. It is anticipated that the concrete work will be complete early next year. Once the podium is completed 4 stories of apartments, using wood construction, will begin. The overall construction is scheduled to be completed in late 2021.